UPDATE (October 16, 2024): Stapleton Road Swimming Pool Demolition

Please be advised that work to remediate and demolish the Old Pool at 3 Stapleton Road has commenced. Access from the main parking lot to the pathway on Davis Place will remain open and will only be closed when necessary for demolition and removal.

The projected timeline for the remediation and demolition is as follows:

Remediation of Hazardous Materials – Ongoing to November 7th 2024

Demolition, Foundation & Soil Excavation – November 8th to 22nd 2024

Backfilling and Site Demobilization – November 22th to 24th 2024