Construction: Kenmount Hill

Share Construction: Kenmount Hill on Facebook Share Construction: Kenmount Hill on Twitter Share Construction: Kenmount Hill on Linkedin Email Construction: Kenmount Hill link

Project Overview

Over the next two years, there will be significant construction occurring in the Kenmount Hill area, including Wyatt Boulevard, Tavenor Place, and Holden Street

These projects include replacing key assets along Farrell Drive, such as the underground water, sanitary, and storm systems. The scope of work for all projects involves construction tie-ins that may encroach onto residential properties. Residents are advised to hold off on driveway paving, landscaping, retaining wall installations, or other similar upgrades that come within one metre of their property line until the projects are complete.


WYATT BOULEVARD

Project Timeline

The construction to upgrade underground infrastructure is expected to begin in June 2025 and continue throughout the remainder of the construction season. Work will resume in 2026.

Work Schedule

The contractor is permitted to work within the hours specified in the City’s Noise Bylaw (7:00 am to 11:00 pm). Daily schedules may vary depending on weather conditions.

What Residents Can Expect During Construction

Traffic Detours

Motorists are advised to follow directional signage and to expect delays at intersections which may be congested due to construction.

Construction Tie-Ins

The scope of work involves construction tie-ins that may encroach onto residential properties. As such, residents are advised to hold off on driveway paving, landscaping, retaining wall installations, or other similar upgrades that come within one metre of their property line until this project is complete.


TAVENOR PLACE

There will be an increase of construction activity on Tavenor Place starting in July 2025. There will be no traffic impacts to residents, but they will see more construction vehicles as they move to the location of the new water tower via Water Tower Access Road.


HOLDEN STREET

Construction on Holden Street is set to being during the 2026 construction season to upgrade the underground infrastructure in the area.


Stay Connected!

  • Project Updates: Get timely news and updates on ongoing and upcoming projects.
  • Schedules and Timelines: Know when work is expected to start and finish in your area.
  • Community Impacts: Stay informed about traffic changes, detours, or other temporary disruptions.

To ensure you never miss an update, we encourage you to subscribe to receive emailed updates on major construction projects in Mount Pearl. Your engagement helps us maintain an open line of communication as we work to improve our city.

Project Overview

Over the next two years, there will be significant construction occurring in the Kenmount Hill area, including Wyatt Boulevard, Tavenor Place, and Holden Street

These projects include replacing key assets along Farrell Drive, such as the underground water, sanitary, and storm systems. The scope of work for all projects involves construction tie-ins that may encroach onto residential properties. Residents are advised to hold off on driveway paving, landscaping, retaining wall installations, or other similar upgrades that come within one metre of their property line until the projects are complete.


WYATT BOULEVARD

Project Timeline

The construction to upgrade underground infrastructure is expected to begin in June 2025 and continue throughout the remainder of the construction season. Work will resume in 2026.

Work Schedule

The contractor is permitted to work within the hours specified in the City’s Noise Bylaw (7:00 am to 11:00 pm). Daily schedules may vary depending on weather conditions.

What Residents Can Expect During Construction

Traffic Detours

Motorists are advised to follow directional signage and to expect delays at intersections which may be congested due to construction.

Construction Tie-Ins

The scope of work involves construction tie-ins that may encroach onto residential properties. As such, residents are advised to hold off on driveway paving, landscaping, retaining wall installations, or other similar upgrades that come within one metre of their property line until this project is complete.


TAVENOR PLACE

There will be an increase of construction activity on Tavenor Place starting in July 2025. There will be no traffic impacts to residents, but they will see more construction vehicles as they move to the location of the new water tower via Water Tower Access Road.


HOLDEN STREET

Construction on Holden Street is set to being during the 2026 construction season to upgrade the underground infrastructure in the area.


Stay Connected!

  • Project Updates: Get timely news and updates on ongoing and upcoming projects.
  • Schedules and Timelines: Know when work is expected to start and finish in your area.
  • Community Impacts: Stay informed about traffic changes, detours, or other temporary disruptions.

To ensure you never miss an update, we encourage you to subscribe to receive emailed updates on major construction projects in Mount Pearl. Your engagement helps us maintain an open line of communication as we work to improve our city.

Questions?

loader image
Didn't receive confirmation?
Seems like you are already registered, please provide the password. Forgot your password? Create a new one now.
  • Share Will Farrell drive be completed by then? If not, the resident won’t be able to get out of the area. Any information would be greatly appreciated. Thank you! on Facebook Share Will Farrell drive be completed by then? If not, the resident won’t be able to get out of the area. Any information would be greatly appreciated. Thank you! on Twitter Share Will Farrell drive be completed by then? If not, the resident won’t be able to get out of the area. Any information would be greatly appreciated. Thank you! on Linkedin Email Will Farrell drive be completed by then? If not, the resident won’t be able to get out of the area. Any information would be greatly appreciated. Thank you! link

    Will Farrell drive be completed by then? If not, the resident won’t be able to get out of the area. Any information would be greatly appreciated. Thank you!

    Tammy Stewart asked 18 days ago
    Hi Tammy, 

    Thanks for your question. The scheduling for the upcoming construction is currently under review to ensure delays are minimal. At this time, construction on Wyatt Boulevard is expected to begin in late June or early July and is not anticipated to overlap with the construction on Farrell Drive.

    We're making efforts to avoid any conflicts that would restrict access for residents, and we'll share updates as the schedule is finalized.