Construction Update: March 27, 2025
Share Construction Update: March 27, 2025 on Facebook Share Construction Update: March 27, 2025 on Twitter Share Construction Update: March 27, 2025 on Linkedin Email Construction Update: March 27, 2025 linkCONSTRUCTION NOTICE
PROJECT OVERVIEW
Starting March 31, 2025, the installation of underground infrastructure for our new Community Centre will affect a portion of the parking lot at the Team Gushue Complex. The work will take place between the main access to the complex and the skatepark.
WHAT TO EXPECT
Access to the skatepark will be limited and temporary closures may be necessary. Access to the rest of the facilities at the Team Gushue Complex will be maintained.
WORK SCHEDULE
The contractor is permitted to work within the hours specified in the City's Noise Bylaw (7:00 am - 11:00 pm). Daily schedules may vary depending on weather conditions.
PROJECT TIMELINE
This localized disruption is expected to last 3-4 weeks and will be complete by the end of April. Other construction activities will continue on the site for the duration of the build.
-
Update: March 10, 2025
Share Update: March 10, 2025 on Facebook Share Update: March 10, 2025 on Twitter Share Update: March 10, 2025 on Linkedin Email Update: March 10, 2025 linkThere’s been some exciting progress on the construction of the community centre at the Team Gushue Sports Complex!
The steel that we received at the end of January is already in place. More steel is coming throughout the month so that the framing process keeps moving forward. The project team is working hard to stay on track with construction set to continue throughout the year to ensure timely completion. Check out the latest photos from the construction site!
-
July 2024 to February 2025
Share July 2024 to February 2025 on Facebook Share July 2024 to February 2025 on Twitter Share July 2024 to February 2025 on Linkedin Email July 2024 to February 2025 linkWe're excited to share this comprehensive video documenting the remarkable transformation of our community centre over the past seven months.
This time-lapse footage captures the dedication and hard work that has gone into creating a space that will serve as a community hub. From groundbreaking and as we work toward completion, watch as this vision comes to life day by day!
This new facility represents our commitment to creating inclusive spaces where community members can gather, learn, and grow together. We look forward to welcoming you all when the doors open!